A KGV is the contracting authority's e-tendering system for a competition, with documents, questions and tenders. Tenders usually go there, not to Doffin.
In Norwegian: KGV (konkurransegjennomføringsverktøy)
Definition
A KGV (konkurransegjennomføringsverktøy) is the e-tendering system the contracting authority uses to run a competition. The word is not in the Public Procurement Act (anskaffelsesloven) or the Public Procurement Regulations (anskaffelsesforskriften); the § references on this page are to the Regulations unless another instrument is named. DFØ (the Norwegian Agency for Public and Financial Management) and Doffin use it, while the Regulations speak of electronic means of communication and of tools and solutions for electronic communication, the «tools and devices» of Directive 2014/24/EU.
In the system, the contracting authority creates the contract notice and sends it to Doffin, the Norwegian national database for procurement notices. It also shares the tender documents there, communicates with suppliers and receives the tenders. DFØ states that contracting authorities today must have a KGV to be able to publish a notice in Doffin and TED (Tenders Electronic Daily), the EU's database of procurement notices, and Doffin only accepts notices from such systems. So Doffin is the database where you find the competition, while the system is where the competition is run. The contracting authority procures the system itself (DFØ), so if you bid for several contracting authorities, you may have to use several systems.
The requirement for electronic communication is in chapter 22 of the Regulations. All communication and information exchange between the contracting authority and the suppliers must be in writing and by electronic means (§ 22-1). Oral communication is allowed if it is documented, but never for the procurement documents, requests to participate, confirmations of interest and tenders. Chapter 22 is in Part III, but it also applies under Part II (§ 8-20), which applies from NOK 1.3 million up to the EEA thresholds (except health and social services), and to special services (særlige tjenester) from NOK 1.3 million with no upper limit, and under Part IV for health and social services (§ 30-1 (6)). The requirement therefore applies at or above NOK 1.3 million, also for special services, but for health and social services only at or above NOK 8.7 million. Between NOK 500,000 and NOK 1.3 million, and for health and social services below NOK 8.7 million, only Part I applies. Part I has no rule on the means of communication. There, in practice, the request for tenders or the tender documents tell you how to submit. Advice: follow what they say. The Utilities Regulations (forsyningsforskriften) have the same requirements in chapter 18, but only in their Part II (contracts at or above the EEA thresholds of NOK 5 million for supply and service contracts and NOK 62.9 million for works) and their Part III (special services and health and social services from NOK 11.6 million) (forsyningsforskriften § 5-1 and § 26-1 (6)); below those values only their Part I applies.
The system must be non-discriminatory, generally available and interoperable with the ICT products in general use, and must not restrict your access to the competition (§ 22-2). No one may have access to the content of the tenders before the time limit has expired, and the exact time when a tender is received must be possible to determine precisely (§ 22-3).
Why it matters for suppliers
You submit your tender where the tender documents say, which in competitions under Part II and Part III is usually the contracting authority's KGV, not Doffin. If you submit in another way than the contracting authority requires, for example by email when submission in the system is required, the tender must be rejected (§ 9-4 in Part II and § 24-1 in Part III). The same applies to a tender that has not been received by the tender deadline.
The following points on submission are advice, not rules. Advice: register in the system early and sign up for notifications, so you get corrections and answers to questions. Advice: read the tender deadline with date and time, and set your own deadline at least one day before. Advice: upload in good time, because large files, many attachments, the ESPD form in competitions under Part III and any electronic signature take time. Under the Regulations, it is the time of receipt that counts (§ 9-4 and § 24-1), not when you started uploading. The moment the system treats as receipt can vary. Advice: check it in the system, check afterwards that all the documents are included, and keep the receipt if the system gives one. Advice: if the system fails, contact the user support and the contracting authority at once, and document the fault with the time. Who bears the risk when the system itself fails is not settled in the sources; see the question on it below.
You send questions during the competition in writing, through the channel the tender documents specify. The contracting authority may require an electronic signature or an electronic seal when you submit the tender, or an electronic means of identification where a third-party submission solution supports it, and the requirements for the level of security must be stated in the tender documents and may not be higher than the risks justify (§ 22-5).
Legal basis
Public Procurement Regulations (anskaffelsesforskriften) § 8-20, § 9-4, § 14-3, § 20-2, § 22-1 to § 22-5, § 24-1, § 25-2 and § 30-1 · Utilities Regulations (forsyningsforskriften) § 18-1 and § 26-1
Example
An IT consultant wants to submit a tender in an open procedure run by a central government directorate, worth NOK 3 million excluding VAT. That is above NOK 1.63 million, the EEA threshold for central government authorities' service contracts, so Part III applies. She finds the contract notice in Doffin and follows the internet address in the notice to the directorate's KGV, where she downloads the tender documents. To submit, she registers her company in the system.
The tender deadline is 1 December at 12:00. She plans to submit the day before, but is delayed and starts uploading at 11:50 on the day of the deadline. The files are large, and the system registers the tender as received at 12:03. The tender has not been received by the tender deadline and must be rejected (§ 24-1). Had she submitted the day before, as she planned, she would have had a day to spare.
Frequently asked questions
Do I submit my tender in Doffin?
No, not in Doffin itself. Doffin is the database for contract notices and only accepts notices from the contracting authorities' systems. Where the tender is to be submitted is stated in the tender documents, and in competitions under Part II and Part III it is usually the contracting authority's KGV. In competitions under Part III, the contract notice must contain the internet address where the tender documents are available (§ 14-3).
Can I send my tender by email?
Normally not. In competitions under Part II, Part III and Part IV, communication must be electronic under chapter 22, and a tender submitted in breach of the requirements on the means of communication must be rejected under Part II and Part III (§ 9-4 and § 24-1). DFØ states that in practice ordinary email has been taken not to meet the security requirements for electronic communication, and according to DFØ, in case 2022/872, a case under Part II, KOFA (the Complaints Board for Public Procurement) took as its basis that it was a breach of the confidentiality requirement when the contracting authority allowed tenders by email. Between NOK 500,000 and NOK 1.3 million, and for health and social services below NOK 8.7 million, only Part I applies, which has no rules on the means of communication. There, in practice, the request for tenders or the tender documents tell you how to submit. Advice: follow what they say.
What happens if the system fails just before the deadline?
It is not settled in the sources read for this page, and they point in different directions. Doffin states that the supplier is responsible for the tender being submitted in time, also when the delay is caused by a technical fault in the system, and that tenders submitted after the deadline must be rejected. DFØ, on the other hand, takes the view that the contracting authority is identified with the provider of the system when the question is whether the rules on electronic communication have been complied with. The Regulations also require that the time of receipt of the tenders can be determined precisely (§ 22-3 (4)). The Regulations say that a tender not received by the tender deadline must be rejected (§ 9-4 (1) in Part II and § 24-1 (1) in Part III), and the wording has no separate exception for faults in the system. How KOFA and the courts treat such cases has not been reviewed here. Advice: submit in good time, so a fault does not hit you in the last hour. Advice: if the system still fails, contact the user support and the contracting authority at once, take screenshots showing the time and keep all communication.
Must I register or pay to get the tender documents?
In competitions under Part III, access must be free of charge, direct and unrestricted (§ 14-3), and DFØ states that the requirement is met when the contract notice or the invitation has the internet address where all the tender documents can be downloaded without a requirement to register. Part II has no equivalent express rule. In competitions under Part II, Part III and Part IV, the contracting authority cannot require an electronic signature or electronic identification for you to get access to the tender documents or to express interest (§ 22-5). If the contracting authority requires a system that is not generally available, it must offer you alternative access, for example free access to the system (§ 22-2 (3)).
When does the contracting authority not have to use electronic communication?
When the nature of the procurement requires specific tools, solutions or file formats that are not generally available, and the contracting authority cannot offer alternative means of access (§ 22-4 (1) letter a). The same applies when the file formats suitable for the tenders cannot be handled by open or generally available software (letter b), when the information requires specialised equipment that is not generally available to the contracting authority (letter c), and for physical models and scale models (subsection (2)). Nor may the contracting authority allow electronic means when other means must be used because of a breach of security in the solution, or because sensitive information cannot be protected well enough (subsection (3)). Where the contracting authority does not require electronic means of communication, post or other suitable carrier must be used (subsection (4)). In competitions under Part III and Part IV, and for special services above NOK 8.7 million, the standstill period (karensperiode) is then at least 15 days instead of 10 when the contracting authority has made an exception from the requirement (§ 25-2, § 10-2 (2) and § 30-9), and in an open procedure under Part III the minimum time limit for tenders is 35 days instead of 30 when tenders are not required to be submitted electronically (§ 20-2).
In Tendline
Tendline assembles the tender in the formats the notice requires, ready for submission →Sources
- Lovdata: Public Procurement Regulations (anskaffelsesforskriften), § 8-20, § 9-4, § 14-3, § 20-2, § 22-1 to § 22-5, § 24-1, § 25-2 and § 30-1 (Norwegian)
- Lovdata: Utilities Regulations (forsyningsforskriften), § 18-1 and § 26-1 (Norwegian)
- DFØ: Guide to the Public Procurement Regulations, chapter 32 Communication (Norwegian)
- DFØ: Digitalisation requirements in public regulations (Norwegian)
- DFØ: Guide to procuring support tools such as KGV and KAV, Support tools in the procurement process (Norwegian)
- Doffin: Frequently asked questions about Doffin and the notice form (Norwegian)
- EUR-Lex: Directive 2014/24/EU on public procurement, Article 22 and Annex IV (English terminology)
Last checked against the sources: 14 October 2026